Driving growth through sustainable


          packaging






          Opal Fibre Australia                                      Stage One construction

          Wodonga.


          In a move to meet growing market demand for sustainable
          fibre packaging, Opal is investing more than $140M
          to construct a state-of-the-art, high speed regional
          manufacturing facility for cardboard packaging.
          Located at the Logic Wodonga industrial estate in Victoria,
          the facility is being constructed in two stages. Stage One
          will deliver a highly automated, sophisticated 47,000m2
          manufacturing site. A future Stage Two would expand the
          site to increase its production capacity.
          Demonstrating Opal’s integrated value chain and
          commitment to circular economy principles, the site will          Investing                   Supporting                        Once
          use recycled and recyclable paper from our Botany and
          Maryvale Mills, to produce sustainable packaging that can        more than                      up to 195                   operational,
          also be recycled.                                               $                              jobs during                  will support
          Construction is expected to be completed by April 2023.           140m                        construction                    432 jobs
          Following fit-out and equipment installation, the site is                                                                  (direct and follow-on)
          expected to begin operating from October 2023.